<?xml version="1.0" encoding="UTF-8"?><rss version="2.0"
	xmlns:content="http://purl.org/rss/1.0/modules/content/"
	xmlns:wfw="http://wellformedweb.org/CommentAPI/"
	xmlns:dc="http://purl.org/dc/elements/1.1/"
	xmlns:atom="http://www.w3.org/2005/Atom"
	xmlns:sy="http://purl.org/rss/1.0/modules/syndication/"
	xmlns:slash="http://purl.org/rss/1.0/modules/slash/"
	>

<channel>
	<title>traversée urbaine de Bamenda Archives - Primeur Hebdo</title>
	<atom:link href="https://primeurhebdo.com/tag/traversee-urbaine-de-bamenda/feed/" rel="self" type="application/rss+xml" />
	<link>https://primeurhebdo.com/tag/traversee-urbaine-de-bamenda/</link>
	<description>Quotidien Panafricain d&#039;Investigations, d&#039;Enquêtes, d&#039;Analyses et d&#039;Informations Générales</description>
	<lastBuildDate>Tue, 06 Oct 2026 13:06:30 +0000</lastBuildDate>
	<language>fr-FR</language>
	<sy:updatePeriod>
	hourly	</sy:updatePeriod>
	<sy:updateFrequency>
	1	</sy:updateFrequency>
	<generator>https://wordpress.org/?v=7.1.3</generator>

<image>
	<url>https://primeurhebdo.com/wp-content/uploads/2026/07/cropped-476386394_1159855992816617_4875671859011920658_n-32x32.jpg</url>
	<title>traversée urbaine de Bamenda Archives - Primeur Hebdo</title>
	<link>https://primeurhebdo.com/tag/traversee-urbaine-de-bamenda/</link>
	<width>32</width>
	<height>32</height>
</image> 
	<item>
		<title>Construction de la traversée urbaine de la ville de Bamenda : les travaux reprennent du rythme.</title>
		<link>https://primeurhebdo.com/construction-de-la-traversee-urbaine-de-la-ville-de-bamenda-les-travaux-reprennent-du-rythme/</link>
					<comments>https://primeurhebdo.com/construction-de-la-traversee-urbaine-de-la-ville-de-bamenda-les-travaux-reprennent-du-rythme/#respond</comments>
		
		<dc:creator><![CDATA[ZAKOUDA]]></dc:creator>
		<pubDate>Tue, 06 Oct 2026 13:06:30 +0000</pubDate>
				<category><![CDATA[ÉCONOMIE]]></category>
		<category><![CDATA[MEZAM]]></category>
		<category><![CDATA[NORD-OUEST]]></category>
		<category><![CDATA[avancement chantier Bamenda]]></category>
		<category><![CDATA[Banque mondiale Bamenda]]></category>
		<category><![CDATA[boulevard urbain Bamenda]]></category>
		<category><![CDATA[Camtel]]></category>
		<category><![CDATA[Camwater]]></category>
		<category><![CDATA[corridor Bamenda-Enugu]]></category>
		<category><![CDATA[infrastructures Nord-Ouest Cameroun]]></category>
		<category><![CDATA[Socadel]]></category>
		<category><![CDATA[travaux Bun's Bamenda]]></category>
		<category><![CDATA[traversée urbaine de Bamenda]]></category>
		<guid isPermaLink="false">https://primeurhebdo.com/?p=6236</guid>

					<description><![CDATA[<p>Les engins ont redémarré sur le linéaire du boulevard urbain de Bamenda. Après une période de ralentissement, l&#8217;entreprise Bun&#8217;s a remobilisé ses équipes sur le terrain il y a quelques&#8230; </p>
<p>The post <a href="https://primeurhebdo.com/construction-de-la-traversee-urbaine-de-la-ville-de-bamenda-les-travaux-reprennent-du-rythme/">Construction de la traversée urbaine de la ville de Bamenda : les travaux reprennent du rythme.</a> appeared first on <a href="https://primeurhebdo.com">Primeur Hebdo</a>.</p>
]]></description>
										<content:encoded><![CDATA[<p>Les engins ont redémarré sur le <a href="https://primeurhebdo.com/construction-de-la-traversee-urbaine-de-la-ville-de-bamenda-les-activites-reprennent-sur-le-terrain/">linéaire du boulevard urbain de Bamenda</a>. Après une période de ralentissement, l&rsquo;entreprise Bun&rsquo;s a remobilisé ses équipes sur le terrain il y a quelques jours. Résultat : les interventions montent en intensité sur les 6,5 km du tracé. Au 4 octobre 2026, le chantier affiche un taux d&rsquo;avancement de 50,09 %, soit une progression notable par rapport aux 44 % enregistrés en juin de la même année.</p>
<h2>Une chaussée qui prend forme</h2>
<p>Sur les points kilométriques 3+825 et 3+950, le gris domine désormais. La raison est simple : la couche de fondation au 0/31,5, épaisseur 20 cm, y a été mise en œuvre. Plus globalement, les travaux de chaussée constituent le gros du travail à réaliser à ce stade du projet.</p>
<p>Les terrassements sont quasiment achevés. La couche de forme est exécutée sur 4,9 km sur les 6,5 km prévus. La plate-forme couvre, quant à elle, 4,6 km. Et la couche de fondation mise en œuvre s&rsquo;étend sur 3,8 km. L&rsquo;entreprise a d&rsquo;ailleurs procédé au réglage de cette dernière, une opération essentielle avant la pose des couches supérieures.</p>
<p>Côté assainissement, les 23 ouvrages hydrauliques prévus sont achevés. Les caniveaux posés couvrent 5 510 mètres linéaires. Des drains sous chaussée ont en outre été engagés du point kilométrique 3+720 au point kilométrique 3+820. Par ailleurs, les équipes poursuivent la mise en place des gabions destinés à la protection du talus au PK 6+175.</p>
<h2>Le déplacement des réseaux, un chantier dans le chantier</h2>
<p>La libération des emprises est quasiment réalisée. Mais un obstacle persiste : le déplacement des réseaux publics. Camwater, Camtel, Socadel. Ces trois opérateurs doivent relocaliser leurs infrastructures pour permettre l&rsquo;élargissement complet de la voie.</p>
<p>Une légère évolution est toutefois constatée sur ce front. Les équipes de Bun&rsquo;s travaillent en coordination avec ces opérateurs pour accélérer la libération des derniers tronçons. Cette étape est cruciale : sans elle, la poursuite des travaux de chaussée sur certaines sections reste bloquée.</p>
<h2>Un projet financé par la Banque mondiale</h2>
<p>Pour rappel, le chantier de la traversée urbaine de Bamenda est financé en grande partie par la Banque mondiale. En juin 2024, l&rsquo;institution a approuvé un financement additionnel de 50 millions de dollars de l&rsquo;Association internationale de développement (IDA) pour soutenir la construction de routes urbaines dans la région du Nord-Ouest.</p>
<p>Ce soutien porte à 242 millions de dollars le montant total des financements de la Banque mondiale en faveur du Projet de développement du secteur des transports au Cameroun. Le corridor Bamenda-Enugu, qui inclut cette traversée urbaine, doit stimuler le commerce avec le Nigeria voisin et renforcer l&rsquo;intégration économique entre les régions du Nord-Ouest et de l&rsquo;Ouest du pays.</p>
<p>Les indemnisations des populations affectées suivent également leur cours. Au total, 3,226 milliards de FCFA ont été mobilisés pour dédommager 119 personnes sur les tronçons Finance Junction-Veterinary Junction-City Chemist et Hospital Roundabout-Meta quarter-T Junction. Un mécanisme de gestion des plaintes, piloté par l&rsquo;ONG CIPCRE, encadre ce processus.</p>
<h2>Cap sur la livraison</h2>
<p>Avec 50,09 % d&rsquo;avancement, le chantier entre dans sa phase la plus visible. Les couches de chaussée se superposent. Les ouvrages hydrauliques sont sortis de terre. Les emprises se libèrent progressivement.</p>
<p>Il reste toutefois des défis. Le rythme des déplacements de réseaux devra s&rsquo;accélérer. La saison des pluies pourrait ralentir certaines opérations. Et la coordination entre les multiples intervenants, Bun&rsquo;s, les opérateurs de réseaux, la mission de contrôle, reste un exercice d&rsquo;équilibre quotidien.</p>
<p>Mais sur le terrain, la dynamique est là. Les équipes sont mobilisées sur plusieurs fronts à la fois. Et le boulevard urbain de Bamenda, maillon stratégique du corridor Bamenda-Enugu, sort peu à peu de terre. Objectif affiché : livrer l&rsquo;infrastructure dans les délais, pour transformer durablement la mobilité dans la capitale régionale du Nord-Ouest.</p>

<a href='https://primeurhebdo.com/wp-content/uploads/2026/10/Construction-de-la-traversee-urbaine-4-scaled.gif'><img fetchpriority="high" decoding="async" width="2560" height="1613" src="https://primeurhebdo.com/wp-content/uploads/2026/10/Construction-de-la-traversee-urbaine-4-scaled.gif" class="attachment-full size-full" alt="" /></a>
<a href='https://primeurhebdo.com/wp-content/uploads/2026/10/Construction-de-la-traversee-urbaine-3-scaled.gif'><img decoding="async" width="2560" height="1613" src="https://primeurhebdo.com/wp-content/uploads/2026/10/Construction-de-la-traversee-urbaine-3-scaled.gif" class="attachment-full size-full" alt="" /></a>
<a href='https://primeurhebdo.com/wp-content/uploads/2026/10/Construction-de-la-traversee-urbaine-2-scaled.gif'><img decoding="async" width="2560" height="1613" src="https://primeurhebdo.com/wp-content/uploads/2026/10/Construction-de-la-traversee-urbaine-2-scaled.gif" class="attachment-full size-full" alt="" /></a>
<a href='https://primeurhebdo.com/wp-content/uploads/2026/10/Construction-de-la-traversee-urbaine-1-scaled.gif'><img loading="lazy" decoding="async" width="2560" height="1613" src="https://primeurhebdo.com/wp-content/uploads/2026/10/Construction-de-la-traversee-urbaine-1-scaled.gif" class="attachment-full size-full" alt="" /></a>

<p>The post <a href="https://primeurhebdo.com/construction-de-la-traversee-urbaine-de-la-ville-de-bamenda-les-travaux-reprennent-du-rythme/">Construction de la traversée urbaine de la ville de Bamenda : les travaux reprennent du rythme.</a> appeared first on <a href="https://primeurhebdo.com">Primeur Hebdo</a>.</p>
]]></content:encoded>
					
					<wfw:commentRss>https://primeurhebdo.com/construction-de-la-traversee-urbaine-de-la-ville-de-bamenda-les-travaux-reprennent-du-rythme/feed/</wfw:commentRss>
			<slash:comments>0</slash:comments>
		
		
			</item>
		<item>
		<title>Construction de la traversée urbaine de la ville de Bamenda : les activités reprennent sur le terrain.</title>
		<link>https://primeurhebdo.com/construction-de-la-traversee-urbaine-de-la-ville-de-bamenda-les-activites-reprennent-sur-le-terrain/</link>
					<comments>https://primeurhebdo.com/construction-de-la-traversee-urbaine-de-la-ville-de-bamenda-les-activites-reprennent-sur-le-terrain/#respond</comments>
		
		<dc:creator><![CDATA[ZAKOUDA]]></dc:creator>
		<pubDate>Sun, 27 Sep 2026 14:50:29 +0000</pubDate>
				<category><![CDATA[ÉCONOMIE]]></category>
		<category><![CDATA[MEZAM]]></category>
		<category><![CDATA[NORD-OUEST]]></category>
		<category><![CDATA[48]]></category>
		<category><![CDATA[80 %]]></category>
		<category><![CDATA[Assainissement]]></category>
		<category><![CDATA[Buns]]></category>
		<category><![CDATA[Cameroun]]></category>
		<category><![CDATA[caniveaux pré-fabriqués]]></category>
		<category><![CDATA[déplacement des réseaux]]></category>
		<category><![CDATA[gabions]]></category>
		<category><![CDATA[protection des talus]]></category>
		<category><![CDATA[travaux Bamenda]]></category>
		<category><![CDATA[traversée urbaine de Bamenda]]></category>
		<guid isPermaLink="false">https://primeurhebdo.com/?p=6085</guid>

					<description><![CDATA[<p>Bamenda, Cameroun. Le chantier de la traversée urbaine affiche un niveau d’exécution de 48,80 % au 27 septembre 2026. Depuis le 22 septembre 2026, les équipes de l’entreprise Bun’s ont&#8230; </p>
<p>The post <a href="https://primeurhebdo.com/construction-de-la-traversee-urbaine-de-la-ville-de-bamenda-les-activites-reprennent-sur-le-terrain/">Construction de la traversée urbaine de la ville de Bamenda : les activités reprennent sur le terrain.</a> appeared first on <a href="https://primeurhebdo.com">Primeur Hebdo</a>.</p>
]]></description>
										<content:encoded><![CDATA[<p>Bamenda, Cameroun. Le chantier de la traversée urbaine affiche un niveau d’exécution de 48,80 % au 27 septembre 2026. Depuis le 22 septembre 2026, les équipes de l’entreprise Bun’s ont repris le travail. Elles se concentrent sur la pose des gabions et la protection des talus.</p>
<h2>Une reprise ciblée sur les gabions et les talus</h2>
<p>Sur le terrain, Bun’s redéploie ses équipes. Celles-ci interviennent au point kilométrique 6+175. Elles effectuent aussi des remises en état au point kilométrique 05+825, à Ayaba street (GRA Down Town). Cette reprise vise à stabiliser les ouvrages et à sécuriser les abords.</p>
<h2>Des emprises dégagées sur 6,3 km</h2>
<p>Par ailleurs, les travaux ont libéré les emprises sur 6,3 km, sur les 6,5 km du linéaire. Les terrassements généraux, presque achevés, couvrent 6,2 km. Ces avancées préparent la suite des opérations.</p>
<h2>Chaussée : des avancées à plusieurs vitesses</h2>
<p>En parallèle, la chaussée progresse. La couche de forme atteint 4,9 km. La plate-forme monte à 4,6 km. La couche de fondation, elle, est mise en œuvre sur 3,7 km. Les équipes avancent donc par étapes.</p>
<h2>Assainissement : 5 416 ml de caniveaux déjà posés</h2>
<p>Toutefois, l’assainissement affiche un résultat concret. Sur 6 500 ml de caniveaux pré-fabriqués, 5 416 ml sont déjà posés. Les 23 ouvrages hydrauliques sont entièrement construits. Ce dispositif doit améliorer <a href="https://primeurhebdo.com/nationale-n5-loum-pont-du-nkam-le-traitement-des-nids-de-poule-saccelere-avant-2027/">l’évacuation des eaux.</a></p>
<h2>Déplacement des réseaux : le vrai point de blocage</h2>
<p>En effet, l’achèvement du chantier dépend d’un facteur clé. Les perspectives reposent sur la fin du déplacement des réseaux. Tant que cette opération n’est pas terminée, le calendrier reste conditionné. Dès lors, les prochaines semaines seront décisives.</p>
<h2>Un chantier à 48,80 %</h2>
<p>Au total, la traversée urbaine de Bamenda avance. Le taux de 48,80 % au 27 septembre 2026 confirme la reprise. Mais le déplacement des réseaux demeure la variable qui fixera la date de livraison.</p>

<a href='https://primeurhebdo.com/wp-content/uploads/2026/10/traversee-urbaine-de-la-ville-de-Bamenda-scaled.gif'><img loading="lazy" decoding="async" width="2560" height="1613" src="https://primeurhebdo.com/wp-content/uploads/2026/10/traversee-urbaine-de-la-ville-de-Bamenda-scaled.gif" class="attachment-full size-full" alt="" /></a>
<a href='https://primeurhebdo.com/wp-content/uploads/2026/10/traversee-urbaine-de-la-ville-de-Bamenda-1-scaled.gif'><img loading="lazy" decoding="async" width="2560" height="1613" src="https://primeurhebdo.com/wp-content/uploads/2026/10/traversee-urbaine-de-la-ville-de-Bamenda-1-scaled.gif" class="attachment-full size-full" alt="" /></a>
<a href='https://primeurhebdo.com/wp-content/uploads/2026/10/traversee-urbaine-de-la-ville-de-Bamenda-2-scaled.gif'><img loading="lazy" decoding="async" width="2560" height="1613" src="https://primeurhebdo.com/wp-content/uploads/2026/10/traversee-urbaine-de-la-ville-de-Bamenda-2-scaled.gif" class="attachment-full size-full" alt="" /></a>
<a href='https://primeurhebdo.com/wp-content/uploads/2026/10/traversee-urbaine-de-la-ville-de-Bamenda-3-scaled.gif'><img loading="lazy" decoding="async" width="2560" height="1613" src="https://primeurhebdo.com/wp-content/uploads/2026/10/traversee-urbaine-de-la-ville-de-Bamenda-3-scaled.gif" class="attachment-full size-full" alt="" /></a>

<p>The post <a href="https://primeurhebdo.com/construction-de-la-traversee-urbaine-de-la-ville-de-bamenda-les-activites-reprennent-sur-le-terrain/">Construction de la traversée urbaine de la ville de Bamenda : les activités reprennent sur le terrain.</a> appeared first on <a href="https://primeurhebdo.com">Primeur Hebdo</a>.</p>
]]></content:encoded>
					
					<wfw:commentRss>https://primeurhebdo.com/construction-de-la-traversee-urbaine-de-la-ville-de-bamenda-les-activites-reprennent-sur-le-terrain/feed/</wfw:commentRss>
			<slash:comments>0</slash:comments>
		
		
			</item>
	</channel>
</rss>